As of December 9 - All windows are installed and look very nice. Most HVAC has been installed. Interior framing and steel doors are complete. All soffitt and fascia installed. All shingles on. Electrician has installed main panel box in basement and is wiring. Propane tank has been donated and will be at the church by end of week. MFA will leak check it and then fill it. Plumbing coming soon. Keep praying for safety of each worker and productivity!!
Thank you to Josh McQueen (excavator), Andy Gingerich (poured basement), Earnest Girod (framer and carport), Willis Redoy (interior framing), Andy Joiner (Electrician), Westons HVAC, Ted Clark (Septic) and Jason Snow (water). All of these men have done a very good job. Thank you!!!
Latest drone pictures taken on November 16.